| Action Date | Action Description |
|---|---|
| Land Evidence Date | |
| Nov 25, 2025 | CHA Worksheet received |
| Nov 25, 2025 | Assent Application Received |
| Dec 01, 2025 | Administrative Review for Completeness |
| Dec 08, 2025 | Eng Team Review for Completeness |
| Dec 08, 2025 | Project Manager |
| Dec 08, 2025 | Application Accepted |
| Dec 18, 2025 | HPHC Historical Preservation No Effect |
| Dec 30, 2025 | Engineering Report |
| Jan 06, 2026 | Typist for Processing |
| Jan 06, 2026 | Permit Approved |
| Jan 07, 2026 | Executive Sign Off |
| Jan 08, 2026 | Permit Mailed |