| Action Date | Action Description |
|---|---|
| HPHC Review Pending | |
| Nov 07, 2025 | CHA Worksheet received |
| Nov 07, 2025 | Assent Application Received |
| Nov 07, 2025 | Administrative Review for Completeness |
| Nov 13, 2025 | Application Accepted |
| Nov 13, 2025 | Eng Team Review for Completeness |
| Nov 13, 2025 | Bio Team Review for Completeness |
| Nov 13, 2025 | Project Manager |
| Nov 25, 2025 | 30 day Public Notice Issued |
| Dec 22, 2025 | Additional Information Received |
| Dec 25, 2025 | Public Notice End Date |
| Dec 31, 2025 | Additional Information Received |
| Jan 22, 2026 | Biologist Report |
| Jan 22, 2026 | Engineering Report |
| Jan 23, 2026 | Typist for Processing |
| Jan 23, 2026 | Executive Sign Off |
| Jan 23, 2026 | Sent to Photo Copy |
| Jan 23, 2026 | PD Amended report mailed. |
| Jan 23, 2026 | Permit Approved |
| Jan 23, 2026 | Permit Mailed |