| Action Date | Action Description |
|---|---|
| Land Evidence Date | |
| Oct 27, 2025 | Assent Application Received |
| Oct 29, 2025 | Administrative Review for Completeness |
| Oct 31, 2025 | Bio Team Review for Completeness |
| Oct 31, 2025 | Deficient Application - Owner Notification Sent |
| Dec 15, 2025 | Deficiency Response Received |
| Dec 29, 2025 | Additional Information Received |
| Dec 29, 2025 | CHA Worksheet received |
| Jan 09, 2026 | Application Accepted |
| Jan 09, 2026 | Project Manager |
| Jan 09, 2026 | Bio Team Review for Completeness |
| Jan 15, 2026 | Biologist Report |
| Feb 05, 2026 | HPHC Historical Preservation No Effect |
| Feb 06, 2026 | Executive Sign Off |
| Feb 06, 2026 | Sent to Photo Copy |
| Feb 06, 2026 | Permit Approved |
| Feb 06, 2026 | Permit Mailed |
| Feb 06, 2026 | Typist for Processing |