| Action Date | Action Description |
|---|---|
| Land Evidence Date | |
| Nov 10, 2025 | Assent Application Received |
| Nov 12, 2025 | Administrative Review for Completeness |
| Nov 17, 2025 | Bio Team Review for Completeness |
| Nov 17, 2025 | Deficient Application - Owner Notification Sent |
| Dec 08, 2025 | Deficient Application Picked Up |
| Jan 06, 2026 | Deficiency Response Received |
| Jan 12, 2026 | Bio Team Review for Completeness |
| Jan 12, 2026 | Application Accepted |
| Jan 12, 2026 | Project Manager |
| Jan 16, 2026 | CHA Worksheet received |
| Feb 04, 2026 | HPHC Historical Preservation No Effect |
| Feb 05, 2026 | Typist for Processing |
| Feb 05, 2026 | Executive Sign Off |
| Feb 05, 2026 | Sent to Photo Copy |
| Feb 05, 2026 | Permit Approved |
| Feb 05, 2026 | Biologist Report |
| Feb 06, 2026 | Permit Mailed |