| Action Date | Action Description |
|---|---|
| Land Evidence Date | |
| Dec 08, 2025 | Assent Application Received |
| Dec 08, 2025 | CHA Worksheet received |
| Dec 10, 2025 | Administrative Review for Completeness |
| Dec 11, 2025 | Bio Team Review for Completeness |
| Dec 11, 2025 | Project Manager |
| Dec 11, 2025 | Application Accepted |
| Jan 07, 2026 | HPHC Historical Preservation No Effect |
| Feb 03, 2026 | Additional Information Requested from Applicant |
| Feb 04, 2026 | Additional Information Received |
| Feb 10, 2026 | Additional Information Received |
| Feb 18, 2026 | Biologist Report |
| Feb 19, 2026 | Typist for Processing |
| Feb 19, 2026 | Executive Sign Off |
| Feb 19, 2026 | Sent to Photo Copy |
| Feb 19, 2026 | Permit Approved |
| Feb 20, 2026 | Permit Mailed |