| Action Date | Action Description |
|---|---|
| Land Evidence Date | |
| Dock Post-Construction Certification by Engineer Required. | |
| Oct 23, 2025 | Assent Application Received |
| Oct 28, 2025 | Administrative Review for Completeness |
| Oct 29, 2025 | Bio Team Review for Completeness |
| Nov 05, 2025 | Project Manager |
| Nov 05, 2025 | Application Accepted |
| Nov 05, 2025 | Eng Team Review for Completeness |
| Nov 13, 2025 | HPHC Historical Preservation No Effect |
| Jan 06, 2026 | Additional Information Received |
| Jan 13, 2026 | 30 day Public Notice Issued |
| Jan 14, 2026 | Correspondence Received |
| Feb 13, 2026 | Public Notice End Date |
| May 12, 2026 | Engineering Report |
| May 13, 2026 | Typist for Processing |
| May 13, 2026 | Executive Sign Off |
| May 13, 2026 | Sent to Photo Copy |
| May 13, 2026 | Permit Approved |
| May 14, 2026 | Permit Mailed |