Action Date Action Description
HPHC Review Pending
Engineering Report
Apr 28, 2026 Assent Application Received
Apr 29, 2026 Administrative Review for Completeness
May 27, 2026 Correspondence Received
Jul 08, 2026 Application Accepted
Jul 08, 2026 Project Manager
Jul 08, 2026 Eng Team Review for Completeness
Jul 10, 2026 30 day Public Notice Issued
Aug 10, 2026 Public Notice End Date

Details:

File No
2026-04-089
Town
Portsmouth
First Name
Malabar Holding Corporation
Last Name
Street
Little Harbor Landing
Location
1 Little Harbor Landing
Plat/Map
43
Lot/Block
5-M
Decision Date
Dock Reg.No
Project
Expand existing structural perimeter limit
Description
Marina Perimeter Limit
Water Area
Easement
0
Acceptance Date
Jul 08, 2026