| Action Date | Action Description |
|---|---|
| Jul 31, 2026 | Assent Application Received |
| Aug 03, 2026 | Administrative Review for Completeness |
| Aug 05, 2026 | Project Manager |
| Aug 05, 2026 | Team Review for Completeness |
| Aug 05, 2026 | Application Accepted |
| Sep 04, 2026 | Correspondence Received |
| Sep 18, 2026 | Geologist Report |
| Sep 21, 2026 | Typist for Processing |
| Sep 21, 2026 | Executive Sign Off |
| Sep 21, 2026 | Sent to Photo Copy |
| Sep 21, 2026 | Permit Approved |
| Sep 21, 2026 | Permit Mailed |