| Action Date | Action Description |
|---|---|
| Feb 13, 2026 | Assent Application Received |
| Feb 27, 2026 | Administrative Review for Completeness |
| Mar 02, 2026 | Additional Information Received |
| Mar 03, 2026 | Bio Team Review for Completeness |
| Apr 24, 2026 | Deficient Application - Owner Notification Sent |
| May 15, 2026 | Deficient Application Picked Up |
| Sep 08, 2026 | Deficiency Response Received |
| Sep 11, 2026 | Bio Team Review for Completeness |
| Sep 11, 2026 | Application Accepted |
| Nov 04, 2026 | HPHC Historical Preservation No Effect |
| Nov 06, 2026 | Finding Of No Significant Impact (FONSI) |
| Nov 09, 2026 | Permit Mailed |