| Action Date | Action Description |
|---|---|
| Land Evidence Date | |
| Dock Post-Construction Certification by Engineer Required. | |
| Jul 02, 2026 | Assent Application Received |
| Jul 07, 2026 | Administrative Review for Completeness |
| Jul 15, 2026 | Bio Team Review for Completeness |
| Jul 15, 2026 | Project Manager |
| Jul 15, 2026 | Application Accepted |
| Jul 15, 2026 | Category A* (Docks) |
| Jul 20, 2026 | Additional Information Received |
| Jul 31, 2026 | HPHC Historical Preservation No Effect |
| Sep 03, 2026 | 30 day Public Notice Issued |
| Oct 03, 2026 | Public Notice End Date |
| Nov 24, 2026 | Typist for Processing |
| Nov 24, 2026 | Executive Sign Off |
| Nov 24, 2026 | Sent to Photo Copy |
| Nov 24, 2026 | Permit Approved |
| Nov 24, 2026 | Biologist Report |
| Nov 25, 2026 | Permit Mailed |