Action Date | Action Description |
---|---|
May 20, 2009 | Assent Application Received |
May 21, 2009 | Administrative Review for Completeness |
May 21, 2009 | Team Review for Completeness |
May 21, 2009 | Team Review for Completeness |
May 21, 2009 | Application Accepted |
May 26, 2009 | 30 day Public Notice Issued |
Jun 23, 2009 | Additional Information Received |
Jun 25, 2009 | HPHC Historical Preservation No Effect |
Jun 26, 2009 | Public Notice End Date |
Jul 22, 2009 | Water Quality Certification |
Jul 31, 2009 | Plans Received |
Sep 01, 2009 | Biologist Report |
Sep 01, 2009 | Engineering Report |
Sep 02, 2009 | Supervisor Biologist SignOff |
Sep 02, 2009 | Supervisor Engineer SignOff |
Sep 03, 2009 | US Army Corp of Engineers Permit Date |
Sep 08, 2009 | Executive Signoff of Staff Reports |
Sep 10, 2009 | Ready to Schedule Semi-Monthly Meeting |
Sep 10, 2009 | Mail Agenda Notice |
Sep 10, 2009 | US Army Corps of Engineers Approval Received |
Sep 22, 2009 | Semi-Monthly Meeting Date Scheduled |
Sep 22, 2009 | Semi-Monthly Meeting Held |
Sep 22, 2009 | Council Approval Granted |
Sep 24, 2009 | Stipulation Package from Biologist |
Sep 24, 2009 | Stipulation Package by Engineer |
Sep 24, 2009 | Permit Issued |
Nov 09, 2009 | Legal Response/Decision |
Oct 24, 2012 | Extension Toll letter mailed |
Jan 24, 2018 | Expiration of Assent/End of Tolling Legislation |