Action Date | Action Description |
---|---|
May 30, 2013 | Assent Application Received |
May 31, 2013 | Administrative Review for Completeness |
May 31, 2013 | Team Review for Completeness |
May 31, 2013 | Application Accepted |
Jun 24, 2013 | Additional Information Received |
Jun 27, 2013 | Correspondence Received |
Jun 27, 2013 | Correspondence Received |
Jul 09, 2013 | HPHC Historical Preservation No Effect |
Jul 18, 2013 | Biologist Report |
Jul 25, 2013 | Typist for Processing |
Jul 25, 2013 | Permit Issued |
Jul 29, 2013 | Executive Sign Off |
Jul 29, 2013 | Sent to Photo Copy |
Aug 20, 2013 | Land Evidence Date |
Mar 23, 2018 | Extension Toll letter mailed |