Action Date | Action Description |
---|---|
Aug 09, 2013 | Assent Application Received |
Aug 12, 2013 | Administrative Review for Completeness |
Aug 27, 2013 | Team Review for Completeness |
Aug 27, 2013 | Deficient Application - Owner Notification Sent |
Sep 10, 2013 | Deficient Application Picked Up |
Sep 24, 2013 | Deficiency Response Received |
Nov 21, 2013 | Team Review for Completeness |
Nov 21, 2013 | Application Accepted |
Dec 04, 2013 | HPHC Historical Preservation No Effect |
Dec 05, 2013 | 30 day Public Notice Issued |
Jan 05, 2014 | Public Notice End Date |
Jan 23, 2014 | Biologist Report |
Jan 24, 2014 | Typist for Processing |
Jan 24, 2014 | Permit Issued |
Jan 27, 2014 | Executive Sign Off |
Jan 27, 2014 | Sent to Photo Copy |
Feb 10, 2014 | Land Evidence Date |
Feb 13, 2014 | US Army Corps of Engineers Approval Received |