Action Date | Action Description |
---|---|
Aug 27, 2013 | Assent Application Received |
Aug 27, 2013 | Administrative Review for Completeness |
Oct 03, 2013 | Team Review for Completeness |
Oct 03, 2013 | Application Accepted |
Dec 04, 2013 | Additional Information Received |
Dec 19, 2013 | Plans Received |
Jan 02, 2014 | Engineering Report |
Jan 02, 2014 | Biologist Report |
Jan 03, 2014 | Typist for Processing |
Jan 03, 2014 | Permit Issued |
Jan 06, 2014 | Executive Sign Off |
Jan 06, 2014 | Sent to Photo Copy |
Jan 16, 2014 | HPHC Historical Preservation No Effect |
Jan 17, 2014 | Land Evidence Date |
Jan 31, 2014 | Water Quality Certification |
Nov 29, 2017 | Modification Request |
Nov 29, 2017 | Administrative Review for Completeness |
Nov 30, 2017 | Team Review for Completeness |
Nov 30, 2017 | Application Accepted |
Dec 18, 2017 | Biologist Report |
Dec 18, 2017 | Typist for Processing |
Dec 18, 2017 | Executive Sign Off |
Dec 18, 2017 | Sent to Photo Copy |
Dec 18, 2017 | Modification Approved |
Jan 08, 2018 | HPHC Historical Preservation No Effect |
Mar 07, 2018 | Duplicate Original Assent requested/mailed |
Mar 09, 2018 | Land Evidence Date |