Action Date | Action Description |
---|---|
Oct 09, 2013 | Assent Application Received |
Oct 10, 2013 | Administrative Review for Completeness |
Oct 17, 2013 | Team Review for Completeness |
Oct 17, 2013 | Deficient Application - Owner Notification Sent |
Mar 13, 2014 | Deficiency Response Received |
Mar 14, 2014 | Team Review for Completeness |
Mar 14, 2014 | Application Accepted |
Mar 14, 2014 | Biologist Report |
Apr 21, 2014 | HPC Historical Preservation Comments/Concerns |
Jun 25, 2014 | Additional Information Requested from Applicant |
Jun 27, 2014 | Certified Receipt Received |
Jul 28, 2014 | Additional Information Received |
Sep 12, 2014 | Plans Received |
Oct 02, 2014 | Permit Issued |
Oct 03, 2014 | Typist for Processing |
Oct 03, 2014 | Executive Sign Off |
Oct 03, 2014 | Sent to Photo Copy |
Nov 03, 2014 | Land Evidence Date |
Apr 24, 2018 | Expiration of Assent/End of Tolling Legislation |