Action Date | Action Description |
---|---|
Mar 05, 2014 | Assent Application Received |
Mar 05, 2014 | Administrative Review for Completeness |
Mar 11, 2014 | Team Review for Completeness |
Mar 11, 2014 | Deficient Application - Owner Notification Sent |
Mar 14, 2014 | Deficient Application Picked Up |
Apr 02, 2014 | Deficiency Response Received |
Apr 03, 2014 | Team Review for Completeness |
Apr 03, 2014 | Team Review for Completeness |
Apr 03, 2014 | Application Accepted |
May 08, 2014 | HPC Historical Preservation Comments/Concerns |
May 14, 2014 | Plans Received |
Oct 16, 2014 | Biologist Report |
Oct 17, 2014 | Typist for Processing |
Oct 17, 2014 | Permit Issued |
Oct 22, 2014 | Executive Sign Off |
Oct 22, 2014 | Sent to Photo Copy |
Nov 07, 2014 | Land Evidence Date |
Oct 25, 2017 | Modification Request |
Nov 17, 2017 | Modification Request |
Nov 17, 2017 | Administrative Review for Completeness |
Nov 20, 2017 | Team Review for Completeness |
Nov 20, 2017 | Application Accepted |
Dec 05, 2017 | HPHC Historical Preservation No Effect |
Dec 11, 2017 | Plans Received |
Dec 21, 2017 | Plans Received |
Dec 27, 2017 | Typist for Processing |
Dec 27, 2017 | Executive Sign Off |
Dec 27, 2017 | Sent to Photo Copy |
Dec 27, 2017 | Modification Approved |
Dec 27, 2017 | Biologist Report |
Jan 16, 2018 | Land Evidence Date |