Action Date | Action Description |
---|---|
Jun 27, 2014 | Freshwater Wetland - Request to Alter |
Jun 30, 2014 | Administrative Review for Completeness |
Jul 31, 2014 | Team Review for Completeness |
Jul 31, 2014 | Deficient Application - Owner Notification Sent |
Aug 05, 2014 | HPHC Historical Preservation No Effect |
Aug 08, 2014 | Deficient Application Picked Up |
Mar 23, 2015 | Deficiency Response Received |
Apr 03, 2015 | Team Review for Completeness |
Apr 03, 2015 | Team Review for Completeness |
Apr 03, 2015 | Deficient Application - Owner Notification Sent |
Apr 13, 2015 | Deficient Application Picked Up |
Apr 20, 2015 | Deficiency Response Received |
Apr 21, 2015 | Team Review for Completeness |
May 11, 2015 | Application Accepted |
Jun 18, 2015 | HPC Historical Preservation Comments/Concerns |
Jul 01, 2015 | Biologist Report |
Jul 01, 2015 | Mail Agenda Notice |
Jul 15, 2015 | Engineering Report |
Jul 28, 2015 | Semi-Monthly Meeting Date Scheduled |
Aug 18, 2015 | Water Quality Certification |
Aug 25, 2015 | Semi-Monthly Meeting Date Scheduled |
Aug 25, 2015 | Council Approval Granted |
Sep 22, 2015 | Legal Response/Decision |
Oct 22, 2015 | Plans Received |
Oct 22, 2015 | Stipulation Package from Biologist |
Oct 22, 2015 | Stipulation Package by Engineer |
Oct 27, 2015 | Typist for Processing |
Oct 28, 2015 | Executive Sign Off |
Oct 28, 2015 | Sent to Photo Copy |
Oct 28, 2015 | Permit Issued |
Feb 23, 2016 | Land Evidence Date |