Action Date | Action Description |
---|---|
Biologist Report | |
Engineering Report | |
Jul 23, 2015 | Assent Application Received |
Jul 24, 2015 | Administrative Review for Completeness |
Aug 17, 2015 | Team Review for Completeness |
Aug 17, 2015 | Team Review for Completeness |
Aug 17, 2015 | Application Accepted |
Sep 16, 2015 | Plans Received |
Sep 21, 2015 | 30 day Public Notice Issued |
Nov 23, 2015 | Additional Information Requested from Applicant |
Jan 13, 2016 | Correspondence Received |
Jan 15, 2016 | Plans Received |
Feb 17, 2016 | Biologist Report |
Feb 22, 2016 | Additional Information Received |
Feb 29, 2016 | Engineering Report |
Mar 01, 2016 | Typist for Processing |
Mar 01, 2016 | Executive Sign Off |
Mar 01, 2016 | Sent to Photo Copy |
Mar 01, 2016 | Permit Issued |
Mar 05, 2018 | Modification Request |
Mar 05, 2018 | Administrative Review for Completeness |
Mar 12, 2018 | Team Review for Completeness |
Mar 12, 2018 | Deficient Application - Owner Notification Sent |
Mar 27, 2018 | Deficiency Response Received |
Apr 03, 2018 | Team Review for Completeness |
Apr 03, 2018 | Application Accepted |
Apr 11, 2018 | HPHC Historical Preservation No Effect |
May 04, 2018 | Additional Information Requested from Applicant |