Action Date | Action Description |
---|---|
Oct 01, 2015 | Assent Application Received |
Oct 01, 2015 | Administrative Review for Completeness |
Oct 01, 2015 | Team Review for Completeness |
Oct 01, 2015 | Team Review for Completeness |
Oct 01, 2015 | Application Accepted |
Oct 15, 2015 | Additional Information Received |
Nov 25, 2015 | HPC Historical Preservation Comments/Concerns |
Dec 18, 2015 | Additional Information Received |
Dec 21, 2015 | HPC Historical Preservation Comments/Concerns |
Jan 08, 2016 | Correspondence Mailed/Faxed/E-mailed |
Jan 14, 2016 | Plans Received |
Jan 22, 2016 | Correspondence Received |
Feb 22, 2016 | Plans Received |
Feb 26, 2016 | Plans Received |
Feb 29, 2016 | Biologist Report |
Mar 02, 2016 | Typist for Processing |
Mar 02, 2016 | Executive Sign Off |
Mar 02, 2016 | Sent to Photo Copy |
Mar 02, 2016 | Permit Issued |
Mar 03, 2016 | Plans Received |
Mar 08, 2016 | HPHC Historical Preservation No Effect |
Jun 01, 2016 | Correspondence Received |
Nov 10, 2016 | Correspondence Received |
Mar 02, 2017 | Correspondence Mailed/Faxed/E-mailed |
Mar 28, 2017 | Plans Received |
Apr 17, 2017 | Plans Received |
May 08, 2017 | Plans Received |
Dec 12, 2017 | Modification Request |
Dec 12, 2017 | Administrative Review for Completeness |
Dec 14, 2017 | Team Review for Completeness |
Dec 14, 2017 | Application Accepted |
Jan 18, 2018 | Additional Information Received |
Mar 06, 2018 | Biologist Report |
Mar 07, 2018 | Typist for Processing |
Mar 07, 2018 | Executive Sign Off |
Mar 07, 2018 | Sent to Photo Copy |
Mar 07, 2018 | Permit Issued |
Mar 14, 2018 | Land Evidence Date |