Action Date | Action Description |
---|---|
Stipulation Package from Biologist | |
Stipulation Package by Engineer | |
Feb 09, 2016 | Assent Application Received |
Feb 09, 2016 | Administrative Review for Completeness |
Feb 10, 2016 | Team Review for Completeness |
Feb 10, 2016 | Team Review for Completeness |
Feb 10, 2016 | Application Accepted |
Mar 01, 2016 | Additional Information Requested from Applicant |
Mar 08, 2016 | HPHC Historical Preservation No Effect |
Mar 11, 2016 | Additional Information Received |
Mar 21, 2016 | 30 day Public Notice Issued |
Apr 13, 2016 | Objections/Comments Received |
Apr 20, 2016 | Objections/Comments Received |
Apr 21, 2016 | Public Notice End Date |
Oct 26, 2016 | Additional Information Requested from Applicant |
Dec 05, 2016 | 30-Day Notification of Cancellation letter |
Dec 21, 2016 | Plans Received |
Apr 13, 2017 | Mail Agenda Notice |
Apr 13, 2017 | Entry of Appearance Received |
Apr 24, 2017 | Letter of Support for Project |
Apr 28, 2017 | Biologist Report |
Apr 28, 2017 | Engineering Report |
May 02, 2017 | Correspondence Received |
May 09, 2017 | Council Approval Granted |
May 09, 2017 | Semi-Monthly Meeting Date Scheduled |
Oct 18, 2017 | Legal Response/Decision |
Oct 18, 2017 | 30 Day Appeal Notification to Owner |