Action Date | Action Description |
---|---|
Apr 01, 2016 | Assent Application Received |
Apr 05, 2016 | Administrative Review for Completeness |
Apr 06, 2016 | Team Review for Completeness |
Apr 06, 2016 | Application Accepted |
Apr 11, 2016 | Plans Received |
Apr 19, 2016 | Additional Information Requested from Applicant |
May 23, 2016 | Plans Received |
May 23, 2016 | HPHC Historical Preservation No Effect |
May 27, 2016 | Biologist Report |
May 27, 2016 | Engineering Report |
May 31, 2016 | Typist for Processing |
Jun 01, 2016 | HPHC Historical Preservation No Effect |
Jun 02, 2016 | Permit Issued |
Jun 02, 2016 | Executive Sign Off |
Jun 02, 2016 | Sent to Photo Copy |
Jun 27, 2016 | Land Evidence Date |