Action Date | Action Description |
---|---|
Jun 23, 2016 | Assent Application Received |
Jun 24, 2016 | Administrative Review for Completeness |
Jun 24, 2016 | Team Review for Completeness |
Jun 24, 2016 | Team Review for Completeness |
Jun 24, 2016 | Application Accepted |
Jun 29, 2016 | Correspondence Received |
Jul 25, 2016 | 30 day Public Notice Issued |
Aug 25, 2016 | Public Notice End Date |
Aug 25, 2016 | Plans Received |
Sep 07, 2016 | HPHC Historical Preservation No Effect |
Oct 31, 2016 | Additional Information Received |
Nov 21, 2016 | Biologist Report |
Nov 23, 2016 | Engineering Report |
Nov 29, 2016 | Mail Agenda Notice |
Nov 30, 2016 | Executive Signoff of Staff Reports |
Dec 13, 2016 | Semi-Monthly Meeting Date Scheduled |
Dec 13, 2016 | Council Approval Granted |
Dec 15, 2016 | Stipulation Package from Biologist |
Dec 15, 2016 | Stipulation Package by Engineer |
Jan 04, 2017 | Typist for Processing |
Jan 04, 2017 | US Army Corps of Engineers Approval Received |
Jan 04, 2017 | Executive Sign Off |
Jan 04, 2017 | Sent to Photo Copy |
Jan 04, 2017 | Permit Issued |
Feb 09, 2017 | Land Evidence Date |
Jun 30, 2017 | Comments Received |
Jan 17, 2018 | US Army Corps of Engineers Approval Received |