Action Date | Action Description |
---|---|
Dock Post-Construction Certification by Engineer received. | |
Mar 23, 2017 | Assent Application Received |
Mar 27, 2017 | Administrative Review for Completeness |
Mar 31, 2017 | Team Review for Completeness |
Mar 31, 2017 | Application Accepted |
Apr 17, 2017 | 30 day Public Notice Issued |
Apr 28, 2017 | HPHC Historical Preservation No Effect |
May 03, 2017 | Public Notice End Date Extension Granted |
May 12, 2017 | Dock Meeting Scheduled (Admin) |
May 12, 2017 | Dock/Section 110 Review approval |
May 17, 2017 | Public Notice End Date |
Jun 01, 2017 | Biologist Report |
Jun 01, 2017 | Typist for Processing |
Jun 01, 2017 | Permit Issued |
Jun 09, 2017 | Land Evidence Date |
Jul 27, 2017 | Additional Information Received |