Action Date | Action Description |
---|---|
May 05, 2017 | Assent Application Received |
May 08, 2017 | Administrative Review for Completeness |
May 09, 2017 | Team Review for Completeness |
May 09, 2017 | Application Accepted |
Jun 05, 2017 | HPHC Historical Preservation No Effect |
Jun 12, 2017 | Additional Information Requested from Applicant |
Nov 06, 2017 | Plans Received |
Nov 14, 2017 | Biologist Report |
Nov 15, 2017 | Typist for Processing |
Nov 15, 2017 | Executive Sign Off |
Nov 15, 2017 | Sent to Photo Copy |
Nov 15, 2017 | Permit Issued |
Dec 01, 2017 | Land Evidence Date |
Feb 13, 2018 | Modification Request |
Feb 13, 2018 | Administrative Review for Completeness |
Feb 14, 2018 | Team Review for Completeness |
Feb 14, 2018 | Application Accepted |
Feb 26, 2018 | HPHC Historical Preservation No Effect |
Mar 26, 2018 | Biologist Report |
Mar 26, 2018 | Typist for Processing |
Mar 26, 2018 | Executive Sign Off |
Mar 26, 2018 | Sent to Photo Copy |
Mar 26, 2018 | Modification Approved |
Apr 25, 2018 | Land Evidence Date |