Action Date | Action Description |
---|---|
Nov 14, 2017 | Assent Application Received |
Nov 14, 2017 | Administrative Review for Completeness |
Nov 15, 2017 | Application Accepted |
Nov 17, 2017 | Team Review for Completeness |
Nov 28, 2017 | HPHC Historical Preservation No Effect |
Jan 17, 2018 | Engineering Report |
Jan 17, 2018 | Typist for Processing |
Jan 17, 2018 | Executive Sign Off |
Jan 17, 2018 | Sent to Photo Copy |
Jan 17, 2018 | Permit Issued |
Feb 07, 2018 | Land Evidence Date |