Action Date | Action Description |
---|---|
Assent Requirement | |
Land Evidence Date | |
Dock Post-Construction Certification by Engineer received. | |
Jan 18, 2018 | Assent Application Received |
Jan 19, 2018 | Administrative Review for Completeness |
Jan 19, 2018 | Category A* (Docks) |
Jan 23, 2018 | Application Accepted |
Jan 23, 2018 | Team Review for Completeness |
Jan 30, 2018 | 30 day Public Notice Issued |
Jan 30, 2018 | Additional Information Requested from Applicant |
Jan 31, 2018 | Plans Received |
Feb 01, 2018 | Correspondence Received |
Feb 02, 2018 | HPHC Historical Preservation No Effect |
Mar 01, 2018 | Public Notice End Date |
Apr 06, 2018 | Biologist Report |
Apr 09, 2018 | Engineering Report |
Apr 09, 2018 | Typist for Processing |
Apr 09, 2018 | Executive Sign Off |
Apr 09, 2018 | Sent to Photo Copy |
Apr 09, 2018 | Permit Issued |