| Action Date | Action Description |
|---|---|
| Dec 16, 2004 | Category A assigned |
| Dec 16, 2004 | Application Accepted |
| Feb 21, 2005 | Typist for Processing |
| Feb 21, 2005 | Executive Sign Off |
| Feb 21, 2005 | Sent to Photo Copy |
| Feb 22, 2005 | Permit Issued |
| Apr 11, 2005 | Land Evidence Date |
| May 17, 2005 | Modification Request |
| May 17, 2005 | Administrative Review for Completeness |
| May 18, 2005 | Team Review for Completeness |
| May 24, 2005 | 30 day Public Notice Issued |
| Jun 09, 2005 | Historical Preservation Approval Granted |
| Jun 15, 2005 | Correspondence Received |
| Jun 20, 2005 | US Army Corp of Engineers Permit Date |
| Jun 24, 2005 | Public Notice End Date |
| Jun 27, 2005 | US Army Corps of Engineers Approval Received |
| Jun 27, 2005 | Biologist Report |
| Jun 27, 2005 | Engineering Report |
| Jul 01, 2005 | Typist for Processing |
| Jul 01, 2005 | Executive Sign Off |
| Jul 01, 2005 | Sent to Photo Copy |
| Jul 01, 2005 | Modification Approved |
| Aug 22, 2005 | Land Evidence Date |
| Sep 16, 2013 | Dock Plate returned/lost |