| Action Date | Action Description |
|---|---|
| Feb 16, 2005 | Assent Application Received |
| Feb 17, 2005 | Administrative Review for Completeness |
| Mar 02, 2005 | Deficient Application - Owner Notification Sent |
| May 27, 2005 | Deficiency Response Received |
| Jun 16, 2005 | Deficient Application - Owner Notification Sent |
| Aug 01, 2005 | Deficiency Response Received |
| Aug 29, 2005 | Team Review for Completeness |
| Aug 29, 2005 | Application Accepted |
| Aug 29, 2005 | Category A* (Docks) |
| Sep 06, 2005 | Historical Preservation Review Required |
| Oct 12, 2005 | 30 day Public Notice Issued |
| Nov 12, 2005 | Public Notice End Date |
| Nov 16, 2005 | US Army Corp of Engineers Permit Date |
| Nov 21, 2005 | US Army Corps of Engineers Approval Received |
| Nov 22, 2005 | Biologist Report |
| Jan 27, 2006 | Dock sub-committee Approved |
| Jan 27, 2006 | Engineering Report |
| Feb 03, 2006 | Typist for Processing |
| Feb 03, 2006 | Executive Sign Off |
| Feb 03, 2006 | Sent to Photo Copy |
| Feb 03, 2006 | Permit Issued |
| May 02, 2006 | Land Evidence Date |
| Jan 21, 2009 | Extension of Permit Request |
| Jan 22, 2009 | Enforcement Compliance Inspection Required |
| Jan 23, 2009 | Process Extension |
| Jan 23, 2009 | Extension Approved |
| Dec 19, 2012 | Extension Toll letter mailed |
| Jan 28, 2013 | US Army Corps of Engineers Approval Received |
| Jun 11, 2013 | Extension Toll letter mailed |