| Action Date | Action Description |
|---|---|
| Mar 18, 2005 | Assent Application Received |
| Mar 24, 2005 | Administrative Review for Completeness |
| Apr 05, 2005 | Team Review for Completeness |
| Apr 05, 2005 | Application Accepted |
| Apr 05, 2005 | Category B assigned |
| Apr 14, 2005 | Correspondence Received |
| Apr 18, 2005 | Historical Preservation Review Required |
| Jun 15, 2005 | 30 day Public Notice Issued |
| Jun 16, 2005 | Additional Information Received |
| Jul 14, 2005 | Correspondence Received |
| Jul 15, 2005 | Objections/Comments Received |
| Jul 15, 2005 | Objections/Comments Received |
| Aug 05, 2005 | Correspondence Received |
| Aug 05, 2005 | Correspondence Received |
| Aug 15, 2005 | Public Notice End Date |
| Apr 21, 2006 | Correspondence Received |
| Jul 17, 2006 | Correspondence Received |
| Oct 30, 2006 | Correspondence Mailed/Faxed/E-mailed |
| Jul 11, 2007 | Additional Information Received |
| Jul 26, 2007 | Correspondence Received |
| Aug 07, 2007 | Correspondence Received |
| Aug 23, 2007 | Correspondence Mailed/Faxed/E-mailed |
| Aug 31, 2007 | Plans Received |
| Aug 31, 2007 | Correspondence Received |
| Nov 13, 2007 | Plans Received |
| Jan 02, 2008 | Mail Agenda Notice |
| Jan 10, 2008 | Correspondence Received |
| Jan 15, 2008 | Council Approval Granted |
| Jan 15, 2008 | Semi-Monthly Meeting Date Scheduled |
| Jan 22, 2008 | Biologist Report |
| Feb 20, 2008 | Historical Preservation Approval Granted |
| Feb 20, 2008 | Water Quality Certification |
| Feb 26, 2008 | Water Quality Certification |
| Mar 11, 2008 | Legal Response/Decision |
| May 23, 2008 | Correspondence Received |
| Sep 26, 2008 | Correspondence Mailed/Faxed/E-mailed |
| Dec 17, 2009 | Additional Information Received |
| Dec 23, 2009 | Permit Issued |
| Dec 23, 2009 | Stipulation Package from Biologist |
| Dec 23, 2009 | Stipulation Package by Engineer |
| Dec 30, 2009 | Conservation Easement Mailed. |
| Jan 05, 2010 | Conservation Easement Recording received |
| Jan 05, 2010 | Land Evidence Date |
| Oct 30, 2014 | Correspondence Received |
| Nov 13, 2014 | Correspondence Received |
| Dec 24, 2014 | Plans Received |
| Jan 08, 2015 | Modification Approved |