| Action Date | Action Description |
|---|---|
| May 10, 2005 | Assent Application Received |
| May 11, 2005 | Administrative Review for Completeness |
| May 13, 2005 | Plans Received |
| May 25, 2005 | Deficient Application - Owner Notification Sent |
| Jun 27, 2005 | Correspondence Received |
| Aug 19, 2005 | Deficiency Response Received |
| Sep 01, 2005 | Team Review for Completeness |
| Sep 01, 2005 | Application Accepted |
| Sep 01, 2005 | Category B assigned |
| Sep 30, 2005 | Historical Preservation Review Required |
| Nov 04, 2005 | Correspondence Received |
| Dec 06, 2005 | Correspondence Received |
| Dec 22, 2005 | Correspondence Received |
| Apr 25, 2006 | Correspondence Mailed/Faxed/E-mailed |
| Aug 30, 2006 | Plans Received |
| Aug 30, 2006 | Category A assigned |
| Sep 25, 2006 | Engineering Report |
| Sep 26, 2006 | Typist for Processing |
| Sep 26, 2006 | Executive Sign Off |
| Sep 26, 2006 | Sent to Photo Copy |
| Sep 26, 2006 | Permit Issued |
| Sep 29, 2006 | Land Evidence Date |
| Sep 17, 2007 | Commencement of Work Notice received |
| Nov 10, 2009 | Correspondence Mailed/Faxed/E-mailed |
| Jul 29, 2010 | Correspondence Mailed/Faxed/E-mailed |