| Action Date | Action Description |
|---|---|
| Nov 01, 2005 | Assent Application Received |
| Nov 02, 2005 | Administrative Review for Completeness |
| Nov 07, 2005 | Team Review for Completeness |
| Nov 07, 2005 | Application Accepted |
| Nov 07, 2005 | Category A* (Docks) |
| Nov 16, 2005 | 30 day Public Notice Issued |
| Nov 29, 2005 | HPHC Historical Preservation No Effect |
| Dec 16, 2005 | Public Notice End Date |
| Jan 11, 2006 | Biologist Report |
| Jan 18, 2006 | US Army Corp of Engineers Permit Date |
| Jan 20, 2006 | US Army Corps of Engineers Approval Received |
| Jan 27, 2006 | Dock sub-committee Approved |
| Jan 27, 2006 | Engineering Report |
| Feb 03, 2006 | Permit Issued |
| Feb 03, 2006 | Typist for Processing |
| Feb 03, 2006 | Executive Sign Off |
| Feb 03, 2006 | Sent to Photo Copy |
| Feb 09, 2006 | Land Evidence Date |
| Oct 16, 2006 | Commencement of Work Notice received |