| Action Date | Action Description |
|---|---|
| Dec 30, 2005 | Maintenance Certification Request |
| Dec 31, 2005 | Administrative Review for Completeness |
| Jan 17, 2006 | Team Review for Completeness |
| Jan 17, 2006 | Application Accepted |
| Jan 18, 2006 | Engineering Report |
| Jan 19, 2006 | Typist for Processing |
| Jan 19, 2006 | Permit Issued |
| Jan 20, 2006 | Executive Sign Off |
| Jan 20, 2006 | Sent to Photo Copy |