| Action Date | Action Description |
|---|---|
| Legal Response/Decision | |
| Apr 25, 2006 | Assent Application Received |
| Apr 26, 2006 | Administrative Review for Completeness |
| May 01, 2006 | Team Review for Completeness |
| May 01, 2006 | Application Accepted |
| May 03, 2006 | Category B assigned |
| May 11, 2006 | 30 day Public Notice Issued |
| May 12, 2006 | HPHC Historical Preservation No Effect |
| Jun 30, 2006 | Public Notice End Date |
| Jul 05, 2006 | Correspondence Received |
| Jul 13, 2006 | Engineering Report |
| Jul 19, 2006 | Additional Information Received |
| Aug 01, 2006 | US Army Corp of Engineers Permit Date |
| Aug 04, 2006 | US Army Corps of Engineers Approval Received |
| Aug 16, 2006 | Biologist Report |
| Sep 19, 2006 | Supervisor Biologist SignOff |
| Sep 19, 2006 | Supervisor Engineer SignOff |
| Sep 20, 2006 | Executive Sign Off |
| Oct 31, 2006 | Ready to Schedule Semi-Monthly Meeting |
| Oct 31, 2006 | Mail Agenda Notice |
| Nov 14, 2006 | Semi-Monthly Meeting Date Scheduled |
| Nov 14, 2006 | Semi-Monthly Meeting Held |
| Nov 14, 2006 | Council Approval Granted |
| Nov 20, 2006 | Stipulation Package by Engineer |
| Nov 21, 2006 | Stipulation Package from Biologist |
| Nov 22, 2006 | Typist for Processing |
| Nov 22, 2006 | Executive Sign Off |
| Nov 22, 2006 | Sent to Photo Copy |
| Nov 22, 2006 | Permit Issued |
| Jan 10, 2007 | Land Evidence Date |
| Jan 10, 2007 | Correspondence Mailed/Faxed/E-mailed |
| Aug 25, 2010 | Modification Request |
| Aug 31, 2010 | Administrative Review for Completeness |