| Action Date | Action Description |
|---|---|
| Aug 30, 2006 | Assent Application Received |
| Aug 31, 2006 | Administrative Review for Completeness |
| Sep 06, 2006 | Deficient Application - Owner Notification Sent |
| Oct 17, 2006 | Deficiency Response Received |
| Oct 18, 2006 | Administrative Review for Completeness |
| Oct 18, 2006 | Team Review for Completeness |
| Oct 18, 2006 | Application Accepted |
| Nov 01, 2006 | HPHC Historical Preservation No Effect |
| Nov 21, 2006 | Correspondence Mailed/Faxed/E-mailed |
| Dec 12, 2006 | Additional Information Received |
| Dec 18, 2006 | Biologist Report |
| Dec 18, 2006 | Engineering Report |
| Dec 19, 2006 | Typist for Processing |
| Dec 19, 2006 | Executive Sign Off |
| Dec 19, 2006 | Sent to Photo Copy |
| Dec 19, 2006 | Permit Issued |
| Jan 09, 2007 | Land Evidence Date |
| Sep 10, 2009 | Modification Request |
| Sep 10, 2009 | Deficiency - Phone Call to Applicant/Owner |
| Sep 17, 2009 | Administrative Review for Completeness |
| Sep 24, 2009 | Team Review for Completeness |
| Sep 24, 2009 | Team Review for Completeness |
| Sep 30, 2009 | Biologist Report |
| Sep 30, 2009 | Engineering Report |
| Sep 30, 2009 | Typist for Processing |
| Sep 30, 2009 | Modification Approved |
| Sep 30, 2009 | Executive Sign Off |
| Sep 30, 2009 | Sent to Photo Copy |
| Oct 05, 2009 | HPHC Historical Preservation No Effect |