| Action Date | Action Description |
|---|---|
| Jun 29, 2007 | Assent Application Received |
| Jul 02, 2007 | Administrative Review for Completeness |
| Jul 13, 2007 | Team Review for Completeness |
| Jul 13, 2007 | Team Review for Completeness |
| Jul 13, 2007 | Deficient Application - Owner Notification Sent |
| Sep 27, 2007 | Deficient Application Discarded/No deficiency Reponse |
| Nov 08, 2007 | Deficiency Response Received |
| Nov 09, 2007 | Administrative Review for Completeness |
| Nov 15, 2007 | Team Review for Completeness |
| Nov 15, 2007 | Team Review for Completeness |
| Nov 15, 2007 | Application Accepted |
| Nov 15, 2007 | Category A* (Docks) |
| Nov 20, 2007 | Plans Received |
| Nov 24, 2007 | HPHC Historical Preservation No Effect |
| Jan 16, 2008 | 30 day Public Notice Issued |
| Feb 16, 2008 | Public Notice End Date |
| Mar 14, 2008 | Dock Meeting -- Approval |
| Mar 24, 2008 | Plans Received |
| Apr 08, 2008 | Biologist Report |
| Apr 08, 2008 | Engineering Report |
| Apr 09, 2008 | Typist for Processing |
| Apr 09, 2008 | Executive Sign Off |
| Apr 09, 2008 | Sent to Photo Copy |
| Apr 09, 2008 | Permit Issued |
| Apr 21, 2008 | Land Evidence Date |
| May 05, 2008 | US Army Corp of Engineers Permit Date |
| May 08, 2008 | US Army Corps of Engineers Approval Received |