| Action Date | Action Description |
|---|---|
| Jul 17, 2008 | Assent Application Received |
| Jul 18, 2008 | Administrative Review for Completeness |
| Jul 18, 2008 | Team Review for Completeness |
| Jul 18, 2008 | Team Review for Completeness |
| Jul 18, 2008 | Application Accepted |
| Aug 07, 2008 | Correspondence Received |
| Aug 08, 2008 | Additional Information Received |
| Aug 14, 2008 | HPC Historical Preservation Comments/Concerns |
| Sep 10, 2008 | HPC Historical Preservation Comments/Concerns |
| Sep 18, 2008 | Additional Information Received |
| Sep 25, 2008 | HPC Historical Preservation Comments/Concerns |
| Oct 01, 2008 | HPHC Historical Preservation No Effect |
| Oct 03, 2008 | HPC Historical Preservation Comments/Concerns |
| Oct 09, 2008 | Additional Information Received |
| Oct 23, 2008 | Biologist Report |
| Oct 23, 2008 | Engineering Report |
| Oct 24, 2008 | Typist for Processing |
| Oct 24, 2008 | Executive Sign Off |
| Oct 24, 2008 | Sent to Photo Copy |
| Oct 24, 2008 | Permit Issued |
| Oct 30, 2008 | Land Evidence Date |
| Nov 10, 2008 | Commencement of Work Notice received |