| Action Date | Action Description |
|---|---|
| Aug 08, 2008 | Assent Application Received |
| Aug 14, 2008 | Team Review for Completeness |
| Aug 14, 2008 | Application Accepted |
| Aug 28, 2008 | 30 day Public Notice Issued |
| Sep 25, 2008 | Dock/Section 110 Review approval |
| Sep 27, 2008 | Public Notice End Date |
| Oct 01, 2008 | Engineering Report |
| Oct 02, 2008 | Typist for Processing |
| Oct 02, 2008 | Executive Sign Off |
| Oct 02, 2008 | Sent to Photo Copy |
| Oct 02, 2008 | Permit Issued |