| Action Date | Action Description |
|---|---|
| Aug 08, 2008 | Assent Application Received |
| Aug 11, 2008 | Administrative Review for Completeness |
| Aug 14, 2008 | Team Review for Completeness |
| Aug 14, 2008 | Team Review for Completeness |
| Aug 14, 2008 | Application Accepted |
| Sep 25, 2008 | HPHC Historical Preservation No Effect |
| Oct 27, 2008 | Plans Received |
| Oct 27, 2008 | Typist for Processing |
| Oct 27, 2008 | Executive Sign Off |
| Oct 27, 2008 | Sent to Photo Copy |
| Oct 27, 2008 | Permit Issued |
| Oct 27, 2008 | Biologist Report |
| Oct 27, 2008 | Engineering Report |
| Oct 28, 2008 | Land Evidence Date |
| Oct 28, 2008 | Commencement of Work Notice received |