| Action Date | Action Description |
|---|---|
| Oct 02, 2008 | Dredge Application |
| Oct 06, 2008 | Administrative Review for Completeness |
| Oct 20, 2008 | Team Review for Completeness |
| Oct 20, 2008 | Application Accepted |
| Oct 31, 2008 | Joint Public Notice |
| Oct 31, 2008 | HPHC Historical Preservation No Effect |
| Nov 07, 2008 | Objections/Comments Received |
| Nov 30, 2008 | Public Notice End Date |
| Dec 29, 2008 | US Army Corp of Engineers Permit Date |
| Dec 30, 2008 | Typist for Processing |
| Dec 30, 2008 | Executive Sign Off |
| Dec 30, 2008 | Sent to Photo Copy |
| Dec 30, 2008 | Dredge Report |
| Dec 30, 2008 | Permit Issued |
| Dec 31, 2008 | Water Quality Certification |
| Dec 31, 2008 | US Army Corps of Engineers Approval Received |
| Feb 20, 2009 | Land Evidence Date |
| Oct 05, 2011 | Extension Toll letter mailed |
| Feb 23, 2012 | Correspondence Mailed/Faxed/E-mailed |