| Action Date | Action Description |
|---|---|
| Dec 23, 2008 | Assent Application Received |
| Dec 29, 2008 | Administrative Review for Completeness |
| Dec 29, 2008 | Team Review for Completeness |
| Dec 29, 2008 | Team Review for Completeness |
| Dec 29, 2008 | Deficient Application - Owner Notification Sent |
| Jan 02, 2009 | Correspondence Received |
| Jan 05, 2009 | Deficiency Response Received |
| Jan 08, 2009 | Administrative Review for Completeness |
| Jan 09, 2009 | Team Review for Completeness |
| Jan 09, 2009 | Team Review for Completeness |
| Jan 09, 2009 | Application Accepted |
| Jan 12, 2009 | Engineering Report |
| Jan 12, 2009 | Typist for Processing |
| Jan 12, 2009 | Executive Sign Off |
| Jan 12, 2009 | Sent to Photo Copy |
| Jan 12, 2009 | Permit Issued |
| Jan 15, 2009 | Additional Information Received |
| Feb 12, 2009 | HPHC Historical Preservation No Effect |
| Feb 17, 2009 | Land Evidence Date |
| Feb 26, 2009 | Commencement of Work Notice received |