| Action Date | Action Description |
|---|---|
| Jul 02, 2009 | Assent Application Received |
| Jul 03, 2009 | Administrative Review for Completeness |
| Jul 07, 2009 | Team Review for Completeness |
| Jul 07, 2009 | Team Review for Completeness |
| Jul 07, 2009 | Application Accepted |
| Jul 07, 2009 | 30 day Public Notice Issued |
| Aug 07, 2009 | Public Notice End Date |
| Aug 25, 2009 | Biologist Report |
| Aug 25, 2009 | Supervisor Engineer SignOff |
| Aug 26, 2009 | Engineering Report |
| Aug 26, 2009 | Supervisor Biologist SignOff |
| Aug 27, 2009 | HPHC Historical Preservation No Effect |
| Aug 31, 2009 | Executive Signoff of Staff Reports |
| Sep 02, 2009 | Ready to Schedule Semi-Monthly Meeting |
| Sep 02, 2009 | Mail Agenda Notice |
| Sep 08, 2009 | Council Approval Granted |
| Sep 08, 2009 | Semi-Monthly Meeting Held |
| Sep 08, 2009 | Semi-Monthly Meeting Date Scheduled |
| Sep 08, 2009 | Category B assigned |
| Sep 09, 2009 | Stipulation Package from Biologist |
| Sep 09, 2009 | Stipulation Package by Engineer |
| Sep 11, 2009 | Typist for Processing |
| Sep 11, 2009 | Executive Sign Off |
| Sep 11, 2009 | Permit Issued |
| Sep 14, 2009 | Sent to Photo Copy |
| Sep 17, 2009 | Land Evidence Date |
| Sep 28, 2009 | US Army Corp of Engineers Permit Date |
| Oct 07, 2009 | US Army Corps of Engineers Approval Received |
| Oct 21, 2009 | Legal Response/Decision |