| Action Date | Action Description |
|---|---|
| Aug 25, 2009 | Assent Application Received |
| Aug 26, 2009 | Administrative Review for Completeness |
| Aug 26, 2009 | Team Review for Completeness |
| Aug 26, 2009 | Team Review for Completeness |
| Aug 26, 2009 | Deficient Application - Owner Notification Sent |
| Sep 01, 2009 | Deficient Application Picked Up |
| Mar 04, 2010 | Deficiency Response Received |
| Mar 08, 2010 | Team Review for Completeness |
| Mar 08, 2010 | Team Review for Completeness |
| Mar 08, 2010 | Application Accepted |
| Mar 25, 2010 | HPHC Historical Preservation No Effect |
| Apr 28, 2010 | Biologist Report |
| Apr 28, 2010 | Engineering Report |
| Apr 29, 2010 | Additional Information Received |
| Apr 29, 2010 | Permit Issued |
| Apr 29, 2010 | Plans Received |
| May 07, 2010 | Land Evidence Date |
| Oct 05, 2010 | Commencement of Work Notice received |
| Jun 11, 2013 | Extension Toll letter mailed |