| Action Date | Action Description |
|---|---|
| Oct 22, 2009 | Maintenance Certification Request |
| Oct 23, 2009 | Administrative Review for Completeness |
| Oct 23, 2009 | Team Review for Completeness |
| Oct 23, 2009 | Team Review for Completeness |
| Oct 30, 2009 | Deficient Application - Owner Notification Sent |
| Jan 04, 2010 | Deficiency Response Received |
| Jan 07, 2010 | Application Accepted |
| Jan 08, 2010 | Biologist Report |
| Jan 08, 2010 | Engineering Report |
| Jan 13, 2010 | Typist for Processing |
| Jan 13, 2010 | Executive Sign Off |
| Jan 13, 2010 | Sent to Photo Copy |
| Jan 13, 2010 | Permit Issued |
| Jan 22, 2010 | Land Evidence Date |
| Sep 20, 2010 | Commencement of Work Notice received |