| Action Date | Action Description |
|---|---|
| Apr 29, 2010 | Assent Application Received |
| Apr 30, 2010 | Administrative Review for Completeness |
| May 06, 2010 | Team Review for Completeness |
| May 06, 2010 | Team Review for Completeness |
| May 06, 2010 | Application Accepted |
| May 06, 2010 | Biologist Report |
| May 06, 2010 | Engineering Report |
| Aug 10, 2010 | Typist for Processing |
| Aug 10, 2010 | Permit Issued |
| Aug 12, 2010 | Executive Sign Off |
| Aug 12, 2010 | Sent to Photo Copy |
| Oct 26, 2010 | Land Evidence Date |