| Action Date | Action Description |
|---|---|
| Dec 24, 2010 | Assent Application Received |
| Dec 29, 2010 | Administrative Review for Completeness |
| Jan 18, 2011 | Plans Received |
| Jan 19, 2011 | Application Accepted |
| Jan 19, 2011 | Team Review for Completeness |
| Feb 03, 2011 | HPHC Historical Preservation No Effect |
| Apr 14, 2011 | Additional Information Received |
| May 04, 2011 | 30 day Public Notice Issued |
| Jun 03, 2011 | Public Notice End Date |
| Jun 16, 2011 | Dock Meeting -- Approval |
| Jun 16, 2011 | Typist for Processing |
| Jun 16, 2011 | Category A* (Docks) |
| Jun 16, 2011 | Permit Issued |
| Jun 16, 2011 | Biologist Report |
| Jun 17, 2011 | Executive Sign Off |
| Jun 17, 2011 | Sent to Photo Copy |
| Jun 22, 2011 | Land Evidence Date |
| Jun 27, 2011 | US Army Corps of Engineers Approval Received |
| Dec 05, 2011 | Modification Request |
| Dec 05, 2011 | Administrative Review for Completeness |
| Dec 19, 2011 | Team Review for Completeness |
| Dec 19, 2011 | Deficient Application - Owner Notification Sent |
| Jan 31, 2012 | Deficiency Response Received |
| Feb 06, 2012 | Team Review for Completeness |
| Feb 09, 2012 | Biologist Report |
| Feb 16, 2012 | Typist for Processing |
| Feb 16, 2012 | Executive Sign Off |
| Feb 16, 2012 | Sent to Photo Copy |
| Feb 16, 2012 | Modification Approved |
| Feb 22, 2012 | HPHC Historical Preservation No Effect |
| Feb 24, 2012 | Land Evidence Date |
| Mar 01, 2012 | US Army Corps of Engineers Approval Received |
| Mar 12, 2012 | Commencement of Work Notice received |