| Action Date | Action Description |
|---|---|
| Jan 19, 2011 | Freshwater Wetland - Preliminary Determination |
| Jan 19, 2011 | Administrative Review for Completeness |
| Jan 20, 2011 | Team Review for Completeness |
| Jan 20, 2011 | Team Review for Completeness |
| Jan 20, 2011 | Application Accepted |
| Feb 03, 2011 | HPHC Historical Preservation No Effect |
| Feb 04, 2011 | Additional Information Received |
| Mar 08, 2011 | Additional Information Received |
| Mar 14, 2011 | Application Accepted |
| Mar 21, 2011 | Typist for Processing |
| Mar 21, 2011 | Biologist Report |
| Mar 21, 2011 | Permit Issued |
| Mar 22, 2011 | Executive Sign Off |
| Mar 22, 2011 | Sent to Photo Copy |
| Apr 19, 2011 | Duplicate Original Assent requested/mailed |
| Apr 25, 2011 | Land Evidence Date |
| Aug 31, 2011 | Monitoring Report |
| Sep 14, 2011 | RIDEM Approval required |
| Sep 14, 2011 | Water Quality Certification |
| Sep 21, 2011 | Water Quality Certification |
| Sep 22, 2011 | US Army Corps of Engineers Approval Received |
| Dec 01, 2011 | Commencement of Work Notice received |
| Jan 30, 2012 | Monitoring Report |
| Jan 30, 2012 | RIDEM Approval required |
| Mar 26, 2012 | Plans Received |
| May 17, 2012 | Water Quality Certification |
| Dec 23, 2013 | Additional Information Received |
| Nov 30, 2015 | Letter of Authorization |
| Oct 26, 2016 | Correspondence Received |
| Nov 09, 2017 | Correspondence Received |
| Nov 16, 2017 | Letter of Authorization |
| Apr 26, 2018 | Correspondence Received |