| Action Date | Action Description |
|---|---|
| Mar 31, 2011 | Assent Application Received |
| Apr 01, 2011 | Administrative Review for Completeness |
| Apr 11, 2011 | Team Review for Completeness |
| Apr 11, 2011 | Deficient Application - Owner Notification Sent |
| Apr 26, 2011 | Deficiency Response Received |
| Apr 26, 2011 | Team Review for Completeness |
| Apr 27, 2011 | Team Review for Completeness |
| Apr 27, 2011 | Application Accepted |
| Apr 29, 2011 | ISDS Approved |
| May 13, 2011 | Permit Issued |
| May 13, 2011 | Biologist Report |
| May 13, 2011 | Typist for Processing |
| May 16, 2011 | HPHC Historical Preservation No Effect |
| May 17, 2011 | Executive Sign Off |
| May 17, 2011 | Sent to Photo Copy |
| May 20, 2011 | Land Evidence Date |
| Jun 24, 2011 | Commencement of Work Notice received |