| Action Date | Action Description |
|---|---|
| Sep 30, 2011 | Assent Application Received |
| Oct 03, 2011 | Administrative Review for Completeness |
| Oct 06, 2011 | Deficiency Response Received |
| Oct 11, 2011 | Team Review for Completeness |
| Oct 11, 2011 | Team Review for Completeness |
| Oct 11, 2011 | Application Accepted |
| Nov 15, 2011 | Plans Received |
| Nov 22, 2011 | 30 day Public Notice Issued |
| Nov 23, 2011 | HPHC Historical Preservation No Effect |
| Dec 20, 2011 | Objections/Comments Received |
| Dec 22, 2011 | Public Notice End Date |
| May 10, 2012 | 30-Day Notification of Cancellation letter |
| May 10, 2012 | Additional Information Requested from Applicant |
| Jun 06, 2012 | Additional Information Received |
| Jun 22, 2012 | 30 day Public Notice Issued |
| Jul 20, 2012 | Correspondence Received |
| Jul 22, 2012 | Public Notice End Date |
| Jul 23, 2012 | Objections/Comments Received |
| Aug 02, 2012 | Objections/Comments Received |
| Aug 21, 2012 | HPHC Historical Preservation No Effect |
| Aug 23, 2012 | Correspondence Received |
| Aug 23, 2012 | Additional Information Received |
| Oct 04, 2012 | Additional Information Received |
| Dec 12, 2012 | Engineering Report |
| Dec 12, 2012 | Water Quality Certification |
| Dec 12, 2012 | Biologist Report |
| Dec 20, 2012 | Supervisor Engineer SignOff |
| Dec 20, 2012 | Supervisor Biologist SignOff |
| Dec 21, 2012 | Executive Signoff of Staff Reports |
| Dec 27, 2012 | Ready to Schedule Semi-Monthly Meeting |
| Dec 27, 2012 | Mail Agenda Notice |
| Jan 08, 2013 | Semi-Monthly Meeting Date Scheduled |
| Feb 20, 2013 | Plans Received |
| Mar 11, 2013 | Plans Received |
| Mar 13, 2013 | Typist for Processing |
| Mar 13, 2013 | Permit Issued |
| Mar 14, 2013 | Executive Sign Off |
| Mar 14, 2013 | Sent to Photo Copy |
| Mar 14, 2013 | Typist for Processing |
| Mar 14, 2013 | Executive Sign Off |
| Apr 11, 2013 | Land Evidence Date |
| May 20, 2013 | Correspondence Mailed/Faxed/E-mailed |
| Sep 03, 2013 | Water Quality Certification |
| Jul 01, 2016 | Extension of Permit Request |
| Jul 08, 2016 | Expiration of Assent/End of Tolling Legislation |
| Jan 18, 2018 | Modification Request |
| Jan 19, 2018 | Administrative Review for Completeness |
| Jan 22, 2018 | Team Review for Completeness |
| Jan 22, 2018 | Application Accepted |
| Feb 02, 2018 | HPHC Historical Preservation No Effect |
| Apr 02, 2018 | Biologist Report |
| Apr 02, 2018 | Engineering Report |
| Apr 02, 2018 | Typist for Processing |
| Apr 02, 2018 | Executive Sign Off |
| Apr 02, 2018 | Sent to Photo Copy |
| Apr 02, 2018 | Modification Approved |
| Apr 23, 2018 | Land Evidence Date |