| Action Date | Action Description |
|---|---|
| Oct 27, 2011 | Assent Application Received |
| Oct 31, 2011 | Administrative Review for Completeness |
| Nov 01, 2011 | Team Review for Completeness |
| Nov 01, 2011 | Application Accepted |
| Dec 27, 2011 | 30 day Public Notice Issued |
| Jan 04, 2012 | HPHC Historical Preservation No Effect |
| Jan 27, 2012 | Public Notice End Date |
| Apr 30, 2012 | Dredge Report |
| Apr 30, 2012 | DEM Dredge Permit |
| May 03, 2012 | Dredge Permit Issued |
| May 07, 2012 | Typist for Processing |
| May 07, 2012 | Executive Sign Off |
| May 07, 2012 | Sent to Photo Copy |
| May 07, 2012 | Permit Issued |
| Jun 01, 2012 | Land Evidence Date |
| Apr 24, 2013 | CAD Cell Fee Due-Final |