| Action Date | Action Description |
|---|---|
| May 07, 2012 | Assent Application Received |
| May 07, 2012 | Administrative Review for Completeness |
| May 07, 2012 | Team Review for Completeness |
| May 07, 2012 | Team Review for Completeness |
| May 07, 2012 | Application Accepted |
| May 11, 2012 | 30 day Public Notice Issued |
| May 16, 2012 | HPHC Historical Preservation No Effect |
| Jun 11, 2012 | Public Notice End Date |
| Jun 15, 2012 | Biologist Report |
| Jun 15, 2012 | Engineering Report |
| Jun 19, 2012 | Supervisor Engineer SignOff |
| Jun 20, 2012 | Executive Signoff of Staff Reports |
| Jun 20, 2012 | Supervisor Biologist SignOff |
| Jul 05, 2012 | US Army Corps of Engineers Approval Received |
| Aug 10, 2012 | Ready to Schedule Semi-Monthly Meeting |
| Aug 10, 2012 | Mail Agenda Notice |
| Aug 28, 2012 | Council Approval Granted |
| Aug 28, 2012 | Semi-Monthly Meeting Date Scheduled |
| Aug 28, 2012 | Semi-Monthly Meeting Held |
| Aug 30, 2012 | Stipulation Package from Biologist |
| Aug 30, 2012 | Stipulation Package by Engineer |
| Sep 10, 2012 | Legal Response/Decision |
| Sep 19, 2012 | Typist for Processing |
| Sep 19, 2012 | Permit Issued |
| Sep 20, 2012 | Executive Sign Off |
| Sep 20, 2012 | Sent to Photo Copy |
| Sep 28, 2012 | Land Evidence Date |